Zoom call held this week (December 13, 2022) during the Sitebuilder Subcommittee meeting time to discuss Project Categories

Attendees
- Ralf Koller (rkoller)
- Leslie Glynn (leslieg)
- Phil Norton (phillipnorton42)
- James Shields (lostcarpark)
- Chris Wells (chrisfromredfin)
- Bob Snodgrass (bsnodgrass)

1. Look at ambiguous examples to see where they fit
https://docs.google.com/spreadsheets/d/1DN351G3BPKJnwttHO6RHb45v9YTkwMTW...

2, Look at scope wordsmithing
https://docs.google.com/spreadsheets/d/1DN351G3BPKJnwttHO6RHb45v9YTkwMTW...

Start all with verb
Change Drupal references to "the site"

Next steps
- Chris to take first pass at finalizing scope including the new agreements.. Rolf to then look at them. Once they agree add to column H for others to review.

Comments

leslieg created an issue. See original summary.

leslieg credited rkoller.

leslieg’s picture

leslieg’s picture

leslieg’s picture

leslieg’s picture

leslieg’s picture

Status: Active » Fixed

Status: Fixed » Closed (fixed)

Automatically closed - issue fixed for 2 weeks with no activity.