Hi,
I am a user who can create and manage my own sites on a aegir platform.
The administrator gave me the permission "view tasks".
I can view my tasks backup, verify and install.
I also view my tasks Disable and Enable when I do it with my site, but I see them both in double (two times).
They point to the same node ID:

Task
Enable -> point to node X
Enable -> point to node X
Disable -> point to node Y
Disable -> point to node Y
Verify -> point to node Z
next page

Have a good day,
Jonathan

Comments

anarcat’s picture

Project: Hostmaster (Aegir) » Hosting
Version: » 5.x-0.2.x-dev

Assigning to the right project (hosting).

adrian’s picture

Status: Active » Fixed

All this code was rewritten, there's now only one of a task type per server|platform|site.