Hello, I have detected that the project bar is not calculating properly the end of the project (It should be the latest task end date)
Comments
Comment #1
Jorge Navarro commentedI just discovered that it's grabbing the next-to-last task's end. So maybe having one "End task" is enough to have the project length calculated.
Comment #2
zaisberger commentedI think it is setting the start date of the task with the latest end date