I'm currently seeing an extra week at the end of the month, kind of like:

I would expect this behavior if I have the week mode set to "fixed" (since that would set it to show exactly 6 weeks), however it's currently set to "liquid". I get the same issue if I use "variable". And oddly enough, the number of weeks do indeed very month to month:

  • 6 in April: Incorrect (too long)
  • 6 in May: Correct
  • 5 in June: Correct
  • 5 in July: Correct
  • 5 in August: Incorrect (too short)
  • 5 in November: Incorrect (too short)

Any ideas? I'd be happy to actively debug / try new things if anyone has a suggestion.

CommentFileSizeAuthor
gsgDM.jpg18.29 KBdavidneedham
Support from Acquia helps fund testing for Drupal Acquia logo

Comments

davidneedham’s picture

Issue summary: View changes
davidneedham’s picture

This is still a problem. Does anyone have any ideas for possible steps to troubleshoot?

davidneedham’s picture

Status: Active » Closed (works as designed)

I checked the version of the fullcalendar jQuery project, and it was 1.6x. I downgraded the version to 1.5x and it seems to have fixed the problem.

davidneedham’s picture

I just came across this again and my fix from #3 worked again. I was really hoping this was no longer an issue.